Posted on: May 14, 2020

UPDATE: SPRING 2020 PAVING - 5/14/2020

UPDATE SPRING 2020 PAVING

5/14/2020


The Town has chosen a contractor to complete its spring 2020 paving.  The Town expects the paving related activities to occur in accordance with this schedule:

May 15 - no parking notices will be posted on Stayman Drive, Blossom Drive, Cobbler Drive, Page Street (north of East Fairfax Street, and East Fairfax Street (between Page Street and First Street).

May 19-20 – milling operations will occur on Stayman Drive, Blossom Drive, Cobbler Drive, Page Street (north of East Fairfax Street0, and East Fairfax Street (between Page Street and First Street).  Milling operations are expected to last until at least mid-day on the 17th.

May 20, 21, and 22 - paving operations will occur on Stayman Drive, Blossom Drive, Cobbler Drive, Page Street (north of East Fairfax Street0, and East Fairfax Street (between Page Street and First Street).

May 22 - no parking notices will be posted on Hermitage Blvd. (between South Church Street and South Buckmarsh Street), Academy Street Extended, Tyson Drive, Lincoln Avenue (from southern terminus to Johnson Williams Middle School entrance), Isaac Court, Lindsay Court, Madden Street, and Montgomery Court.

May 26-27 - milling operations will occur on Hermitage Blvd. (between South Church Street and South Buckmarsh Street), Academy Street Extended, Tyson Drive, Lincoln Avenue (from southern terminus to Johnson Williams Middle School entrance), Isaac Court, Lindsay Court, Madden Street, and Montgomery Court.  Milling operations are expected to last until at least mid-day on the 27th.

May 27, 28, and 29 - paving operations will occur on Hermitage Blvd. (between South Church Street and South Buckmarsh Street), Academy Street Extended, Tyson Drive, Lincoln Avenue (from southern terminus to Johnson Williams Middle School entrance), Isaac Court, Lindsay Court, Madden Street, and Montgomery Court. 


PLEASE NOTE:

Notices - Because of COVID-19, no door hangers will be posted in these areas.  Posting will occur only along the street.

Changes in schedule – the dates provided above and on posted notices are subject to change.  Weather delays, mechanical failures, and the like may require changes in the project schedule.

If you have any questions about this matter, then please contact Rick Boor, Public Works Director at directordpw@berryvilleva.gov.