Weather permitting, milling and paving operations are expected to begin soon. The tentative schedule for paving follows:
Fremont Court and Hancock Court: Work to begin on Friday, May 24. Work on these streets should take one to one and a half days.
Hermitage Boulevard: Work to begin on Friday, May 24. Work on this street should take two to three days.
It is expected that paving will be completed by May 31st.
Line painting is expected to occur approximately seven days after paving is completed.
Parking restrictions will be in effect through the duration of the project.
We apologize for any inconvenience. If you have any questions, please call Rick Boor, Director of Public Works, at (540)955-4843.