Posted on: May 20, 2021

[ARCHIVED] Street Paving Operations

Street Paving Operations

 

Street paving operations in Berryville will soon begin. 

 

The paving operations are expected to be conducted in accordance with the schedule below:

 

Street or Street Section       Milling Date(s)                       Paving Date(s)

 

Circle Drive                                         5/24                                         5/24-25

Ridge Road                                         5/24                                         5/24-25

Rockcroft Drive & the

     400 block of North Church St        5/24                                         5/24-25

West Fairfax Street                             5/24                                         5/24-25

Chalmers Court                                   5/25-26                                    5/26

Blue Ridge Street                               5/26                                         5/27

Litten Court                                         5/27                                         5/27

Turner Court                                       5/27                                         5/27

Harriman Court                                   5/27                                         5/28

 

 

The schedule provided above is subject to change because of inclement weather, mechanical failure, or other reasons. Generally, if operations are canceled in an area, then work will resume the next work day.

 

Parking restrictions will be posted in affected areas at least 48 hours prior to commencement of work.

 

No operations will occur on Saturdays, Sundays, or Town-recognized holidays.

 

Pease contact Rick Boor, Director of Public Works, at directordpw@berryvilleva.gov or 955.4843 if you have any questions about this matter.